We’re getting closer and closer to the finish line, and there’s been a LOT of progress at your new library! Here’s what’s happening:

  • All flooring is now installed! Baseboards are in progress.
  • Electrical work is nearly complete except for the pendant lights.
  • The parking lot is paved and painted!
  • Landscaping is underway! The landscaper will be out this week.
  • Our solar project is moving forward! Preparations are underway, with the panel installation to be scheduled after we take occupancy of the building.
  • Data wiring prep begins this week! This will help get the building ready for all the technology and connectivity our new library will offer.
  • Automatic door hardware will be scheduled for installation soon.

Every day, we’re seeing more and more of our new library come together – and we can’t wait to welcome you inside! Thank you for continuing to support us as we work toward the opening of your new Sewickley Township Public Library!